Party wall notices responding options
Contents |
[edit] Introduction
Once adjoining owners are served with a Party Wall Notice they have a couple of different options for how they can respond. They can either consent or dissent to the works, however, the ramifications of these choices are more complex then they may seem.
[edit] Consenting to the Party Wall Notice
When an adjoining owner goes with the consent option, they are stating that they are agreeable with the building owner’s Party Wall works going ahead without a Party Wall Award being written up and served upon the respective owners. This is generally the preferred option for building owners as it means they do not need to pay for a Party Wall Surveyor and they can start the Party Wall works on-site immediately.
As an adjoining owner, if for whatever reason you trust the works will be done without damage, and if any damages are caused the building owner would pay for repairs, then this is the option to go for.
However, if there is doubt as to whether the works will cause damage, or whether the building owner would rectify any issues, this is probably not the preferred option.
As a Party Wall Award will not be written up, you will have little control over how to works themselves are undertaken, and, unless you get a Surveyor’s Schedule of Condition Report prepared and written up pre works, there will be no record of your property before the works were undertaken. This means that if damages do occur, it will be harder to prove they were caused as a result of the work and could place you in a compromised situation when it comes to claim for any damage.
[edit] Dissenting to the Party Wall Notice
When an adjoining owner dissents, they are stating that they do not want the building owner’s proposed Party Wall works to go ahead without a Party Wall Award first being written up and served by a Party Wall Surveyor, or Party Wall Surveyors depending upon the response option they select.
Adjoining owners often feel safer having more protection in place should there be issues with the works. This is not only beneficial for adjoining owners however, as building owners can protect themselves from false claims of damages and issues with the works such as gaining access.
Once the Party Wall Notice dissent option is picked, that means that Schedule of Condition Reports will need to be carried out, and Party Wall Awards written up and served. This will be carried out by either an Agreed Surveyor or by the Building Owner’s Surveyor and Adjoining Owner’s Surveyor in unison, depending upon whether the Adjoining Owner opts for their own Party Wall Surveyor or agrees to share the same one as the Building Owner. Once the award is written up and served, and only then, may the Party Wall works commence.
Going down this route is, of course, more time-consuming and costly for the Building Owner, and for this reason Building Owners often push for the Party Wall Notice Consent option. However, dissenting to the Notice and getting the Party Wall Award written up is definitely the safer option and offers the all invaluable peace of mind that many owners seek, while also offering protection for both the Building Owner and Adjoining Owner.
If you do trust your neighbour and do want to go for a Party Wall Notice consent, it can be sensible to get a Surveyor’s Schedule of Condition Report written up at the very least. This will provide you obtain sufficient evidence in case damages do occur, which can help you in any claims that you may need to make.
[edit] Related articles on Designing Buildings Wiki
- 10(4) Party Wall Surveyor Appointments.
- Adjoining buildings definition.
- Fence.
- Institute of party wall surveyors.
- Line of junction notice.
- Party structure notice.
- Party wall act.
- Party wall surveyor.
- Preventing wall collapse.
- Responsibility for boundary features.
- Right of entry.
- Right of support.
- Right to access land.
- Trespass.
- Wall types.
- What approvals are needed before construction begins.
- Who Pays for Party Wall Surveyor's Fees?
Featured articles and news
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.